Forest Service closing in on final Rosemont report
Monday, November 19th, 2012In a meeting for press and legislators on Friday, November 16, Coronado Forest Supervisor Jim Upchurch announced that the Forest Service would not be releasing its Final Environmental Impact Statement on the Rosemont copper project in December, 2012, as planned. He would not speculate on a new date for the report. The Forest Service released its Draft Environmental Impact Statement in October, 2011, and has since received more that 25,000 comments from the public according to Upchurch. Upchurch is being very cautious and thorough to make sure the Forest Service meets its responsibility according to law. At the meeting, both opponents and proponents of the mine expressed frustration on the length of the process.
To begin mining, Rosemont Copper must obtain approvals and permits from local, state, and federal agencies. Rosemont started the process in July, 2006. I commented on this bureaucratic quagmire in my post: Mining and the bureaucracy.
Upchurch attributed the delay to pending action by several agencies:
U.S. Fish & Wildlife Service (FWS) is considering listing as endangered, or imposition of critical habitat for the jaguar, ocelot and several other species. Under the Endangered Species Act, the Forest Service must complete a “section 7 consultation” with FWS before it can issue a decision. Upchurch anticipates a decision from FWS in January or February, 2013. Note that Arizona Game & Fish recommends that FWS withdraw its proposal for jaguar critical habitat (see here), because “conservation of the species is entirely reliant on activities in the jaguar’s primary habitat of Central and South America to be successful. Lands in Arizona and New Mexico make up less than one percent of the species’ historic range and are not essential to the conservation of the species.”
The Environmental Protection Agency (EPA) is still considering air quality impact due to particulate matter that may be released by the mining operation. Rosemont will submit updated air quality models this month. It is anticipated that Arizona Department of Environmental Quality will issue its air quality permit in December, which will probably show that Rosemont is in compliance with all state and federal regulations.
The Forest Service must coordinate with the Corps of Engineers concerning impacts on waterways, but this is somewhat of a circular argument since the Corps of Engineers can’t issue an opinion until it sees the Forest Service’s Final Environmental Impact Statement.
There are issues with 11 Indian Tribes. The mine site is alleged to contain up to 80 cultural sites, including burial sites, that must be considered and mitigated according to the National Historic Preservation Act.
Upchurch said that the process is about 85% to 90% complete. That would seem to preclude calls for starting all over again, something which Pima County and Representative Ron Barber have been promoting. Upchurch also said that the water issues are “mostly” resolved. What remains are mitigation for possible impacts to a few nearby water wells. Upchurch sees nothing in the water issue that would preclude the Forest Service from issuing its final report.
At the meeting, one “reporter,” John Dougherty, producer of an attack documentary film against Rosemont, several times commented that Rosemont’s proposed dry stacking method for tailings would result in the largest such dry stacked tailings dump in the world. Dougherty was implying some imagined danger. However, dry stacking of tailings is a much more stable method than conventional wet tailings. It also saves and recycles water. (See my post on dry stacking here.) This is an example of one of the many spurious issues with which Rosemont and the Forest Service have to contend. Dougherty’s comments got no traction from Upchurch.
In general, Upchurch said that as they get more and more information, the information shows that the mining project will have fewer detrimental impacts than some fear or allege.
See reporter Tony Davis’ take on the meeting in the Arizona Daily Star here.
As Tony quoted me in his article: “The process to approve this mine seems endless, and many people are frustrated. ..Maybe it means the laws controlling the process need to be changed.” Indeed, much of the delay is caused by inefficiency and lack of coordination in and among federal agencies. The Rosemont saga is nearing its seventh year in bureaucratic purgatory. Meanwhile, the projected benefits for jobs and our economy remain deferred.